SAP PP (Production planning)
Master Data
The word
master data indicates that it is a data we need to maintain in SAP system for product
structure, processes, capacity planning and availability of material. The master
data control planning and execution processes. Master data is an important part
of any SAP module, It can be crucial for success or failure of implementation.
The important
master data in SAP PP are Material master,
Bill of material (BOM), Routing and Work center. Sometimes we use production
version to minimize efforts and take advantages of selection of master data,
production version is combination of BOM and Routing.
1. Material Master
Material Master Data having all the information related to different
material type like Finish material, Semi-finish material, Raw material, Spare parts
and Packaging material. Here we maintain basic data, material requirement planning
data (MRP), Purchasing data and etc.
T-code for Master Data: MM01 – Creation
MM02 – Change
MM03- Display
Path: SAP menu > Logistic > Production >
Master data > Material > Create (Immediately)
2. Bill Of Material:
BoM is a list of all necessary components/ Material which is required for
final product or assembly. The BOM contain structural relationship among the
individual component according to BOM type. Discrete and repetitive industry it
is use as BOM where in process industry it is known as recipe. We can create up
to 99 BOM.
T-Code for BOM: CS01 – Create
CS02 – Change
CS03 – Display
Path: SAP menu > Logistic > production >
Master Data > Bill of Material > Bill of material > Material BOM >
Create.
3. Routing:
Routing is sequence of activities to convert raw material to finished
product. The sequence of all activities performed at work center. We can describe what is to be
produced, in what fashion, and what materials are needed for the production. Using
routing we can calculate production cost, machine time and labor time.
T-code for routing: CA01 – Create
CA02 – Change
CA03 – Display
Path: SAP menu > Logistic >
Production > Mater data > Routings > Routings > Standard Routing
> Create.
4. Work Center:
Work Center is a place where all production work can be perform. It is play an important
role to represent the central capacity quantity within production planning. The
work center can be used for activities like scheduling, production costing and
Capacity planning.
T-Code for Work center: CR01 – Create
CR02 – Change.
CR
03 – Display
Path: SAP menu > Logistic >
Production > Master data > Work center > Work center > create.